PIP in Portugal: secure a plot before you buy it
The PIP (pedido de informação prévia, prior information request) is the Portuguese town hall's official answer on whether a building project is feasible. For a foreign buyer, it turns a hunch ("this plot looks buildable") into a written commitment from the authorities. This guide covers what it contains, what it costs, how long it takes under the rules in force since 1 October 2026, and how to use it before you sign for a plot.
What a PIP is
In England, the closest idea is outline planning permission; in the US, a zoning verification letter or a pre-application determination. You describe a specific project on a specific plot; the câmara answers formally whether that project can be authorised under the PDM (the municipal zoning plan) and the constraints that apply. The full authorisation procedure (licenciamento, or a prior communication) comes afterwards, but its framework is already settled.
The 2026 reform: what changed
The planning code (RJUE) was revised by Decree-Law 108/2026 of 29 May, in force since 1 October 2026 after a two-month postponement. For the PIP, four points matter to a buyer:
| Point | Rule since 1 October 2026 | RJUE article |
|---|---|---|
| Deadline for the answer | 15 days for a simple request; 30 days for a detailed request (45 for a subdivision), counted after the preliminary check of the file; when outside bodies must be consulted, from their last opinion | 16(1) and 16(2) |
| No answer in time | The request is deemed approved (tacit approval) | 16(6) |
| Unfavourable answer | Must state how the project, if viable, could be revised to comply | 16(5) |
| Favourable answer | Binds the authorities; a detailed request covering all the points of article 14(2) even exempts the works from a permit or prior communication, if you build exactly what was assessed | 17(1) and 17(2) |
| Time to act | Two years to file the permit application or start the works; then one confirmation request to the mayor, followed by one more year | 17(5) to 17(7) |
The legal deadlines are maximums. Ask the câmara how long its files actually take: the preliminary check and any outside consultations come before the clock starts.
What goes in the application
A PIP is filed with the câmara of the municipality where the plot lies, online or at the counter depending on the municipality. Since the reform, standard application forms are set by ministerial order. The file is light compared with a full permit:
- Description of the project: intended use (housing, tourism, etc.) and main features;
- Siting: position of the building on the plot, access, setbacks;
- Areas: planned floor area and footprint;
- Heights: number of storeys and facade height;
- Plot documents: identification of the plot and a location plan.
In practice, the core of the file is two documents: the planta de localização (location plan), which places the plot on the municipal map, and the memória descritiva (descriptive note), a short text describing the project: use, areas, storeys, access, planned connections. The more precise the description, the more concrete the commitment you get; a vague PIP gets a vague answer. A local architect or design office prepares these documents in a few weeks. The municipal fees vary by municipality and run to a few hundred euros, nothing compared with the price of the land they secure.
Reading the answer: three scenarios
Favourable
The câmara approves the project as described, and states which procedure the works will follow. The commitment covers exactly what was in the request: if you later increase the area or add a storey, you leave the protected framework. Good practice: keep the PIP parameters as the basis of the architect's design, and file within the two-year window.
Favourable with conditions
The câmara accepts the principle but sets conditions: an extra setback, a height limit, connections to build, sometimes a strip of land to give up for road widening. Each condition has a cost or an effect on the plan: have the architect price them before you lift the purchase condition. An acceptable condition makes the answer as useful as a plain approval; a costly one is negotiated into the price of the land.
Unfavourable
The decision gives its reasons: the plot's PDM class, a protected reserve (REN or RAN, the national ecological and agricultural reserves), an easement, insufficient access. Since the reform, it must also say how a viable project could be revised. If the reason is the project (too big, badly sited), a revised PIP can succeed. If the reason is the land itself (an unbuildable class), a conditional promissory contract does its job: the deposit comes back and the search goes on elsewhere, for a few hundred euros of fees instead of the price of the land.
The strategic use: a condition in the CPCV
In Portugal, buying land usually goes through a CPCV (contrato-promessa de compra e venda, promissory contract). The practice that protects the buyer is to write in a condition tied to the PIP: the sale only completes if the câmara answers favourably on the project described. Three benefits:
- you reserve the plot while the PIP is examined;
- if the answer is favourable, you buy with a building framework secured for two years;
- if it is not, the contract falls away and your deposit comes back under its terms.
Set the CPCV timetable on the PIP's: allow for the preliminary check, any consultations and the legal deadline, then a margin for the architect to read the decision before the deed. The contract should also say who files the PIP and who pays: in practice the buyer, since the answer protects them. The written decision also helps with financing: a bank prefers lending on a plot whose buildability is confirmed by the câmara rather than assumed.
When a PIP is not needed
The PIP is optional, and some situations make it unnecessary, in particular a plot in a subdivision covered by a recent alvará de loteamento (subdivision permit): building rights are already defined plot by plot (areas, siting, heights). Checking the permit and its rules is then enough. Elsewhere, especially for isolated plots or listings that say "buildable" with no document to back it, the PIP remains the step that gives the fullest protection before buying. To read the PDM and the zoning first, see can you build on that land?, and for the whole purchase, buying land in Portugal.
Have this plot checked before you buy
We check the three registers and the municipal zoning plan (PDM) for you, and you receive a written report in English within 72 hours: the registered owner, charges and mortgages, zoning, area discrepancies, and the exact questions to ask the seller.
Just tell us where the plot is: you receive your payment link by email.
Request received. Within a few minutes you receive an email with what happens next and your secure payment link. No work starts before payment. If it is not there, check your spam folder.
Payment link by email · refunded in full if the documents for your plot cannot be obtained · your data is used only to handle this request (terms of sale, privacy policy in French).
Frequently asked questions
Is a PIP compulsory before buying land?
No, it is optional. It becomes strongly advisable as soon as the plot is outside a recent approved subdivision: it is the only document that commits the câmara on the feasibility of your specific project.
How long is a favourable PIP valid?
You have two years from the notification of the favourable decision (or from the tacit approval) to file your permit application, or to start the works if your PIP exempts you from a permit (RJUE, article 17(5), as amended by Decree-Law 108/2026). After that, you can ask the mayor once to confirm that nothing has changed; if confirmed, you have one more year.
Can I apply for a PIP without owning the plot?
Yes. Any interested person can apply for a PIP on a plot, which is exactly what lets you use it before buying, alongside the promissory contract.
What happens if the câmara does not answer in time?
Since 1 October 2026, if the legal deadline passes without a decision, the PIP is deemed approved (tacit approval, RJUE article 16(6)). Your title is then the filed application plus proof of submission and of the fees paid.
Does a favourable PIP guarantee the permit?
It binds the authorities on the project as described. If your application covered all the points listed in article 14(2) of the RJUE, the favourable PIP even exempts the works from a permit or prior communication, provided you build exactly what was assessed. Any significant change takes you back to the full procedure.